Overview
40 Lots Staked in Three Days
Copper Ridge Homes broke ground on a 40-lot subdivision in Erie with foundations scheduled back-to-back. Our job: full construction staking — lot corners, building envelopes, utilities and curb — plus as-builts for closeout.
40
Lots Staked
3
Days On Site
0
Restakes Needed
Challenge
A Compressed Schedule on Fresh Grading
Mass grading finished just days before foundations were due, leaving soft ground, shifting curb lines and a survey control network buried under fresh fill. Any staking error would cascade across 40 foundations.
Approach
Control First, Then Speed
We re-established primary control from off-site monuments, ran a closed GPS network across the site, then deployed two robotic crews staking in parallel — lot lines one day, envelopes and utilities the next, curb and final checks on day three.
Cut sheets hit the superintendent's inbox each evening; every foundation fit the plat to the inch.
Deliverables
Lot staking, utility and curb stakes, foundation as-builts, final plat support.
Result
All 40 foundations poured on schedule with zero restakes — the developer's fastest phase to date.